Cabinet Approves ₹2,814 Crore Scheme for Lithium and Nickel Processing Plants

₹2,814 crore critical mineral processing scheme: 30% capex subsidy for 2 lithium and 2 nickel plants, caps, selection, tranches and expected impact.

By Business
Cabinet Approves ₹2,814 Crore Scheme for Lithium and Nickel Processing Plants

The Union Cabinet has approved a ₹2,814 crore scheme to help companies build lithium and nickel processing plants in India. The Capex Support Scheme to Promote Critical Mineral Processing was cleared on 4 November 2026 at a meeting chaired by Prime Minister Narendra Modi. It will pay a 30% capital subsidy to four processing plants, two for lithium and two for nickel, between FY 2026-27 and FY 2030-31. The government expects the scheme to draw about ₹10,000 crore of investment. The goal is to cut India’s reliance on imported battery-grade materials used in electric vehicles, energy storage, electronics, defence and speciality steel.

The scheme at a glance

  • Outlay: ₹2,814 crore, fully funded from the Union Budget

  • Period: Five years, FY 2026-27 to FY 2030-31

  • Support: Capital subsidy of 30% of eligible investment

  • Plants covered: Two lithium units with a minimum of 30 kt capacity apiece, and two nickel units with a minimum of 50 kt apiece

  • Cap per beneficiary: ₹500 crore for lithium and ₹900 crore for nickel

  • Selection: Technical qualification first, then bidding on the lowest subsidy sought

  • Nodal ministry: Ministry of Mines

How the ₹2,814 crore is split

Component

Per beneficiary (max)

Beneficiaries

Total

Lithium processing

₹500 crore

2

₹1,000 crore

Nickel processing

₹900 crore

2

₹1,800 crore

Administrative expenses (0.5%)

—

—

₹14 crore

Total outlay

₹2,814 crore

What the plants will produce

The lithium plants will turn ores and concentrates into battery-grade lithium products. Brines are not covered. The nickel plants will make either Class-1 nickel or battery-grade nickel sulphate, and recover cobalt as a by-product. These high-purity materials are the inputs for battery materials, battery cells and speciality steel. India currently imports most of them.

How companies will be selected

Selection happens in two stages:

  1. Technical qualification: Every application is first checked against technical criteria. Only applicants who qualify move to the next stage.

  2. Financial bid: Qualified applicants bid for support. The winner is the one that asks for the lowest capital subsidy (a least-cost rule). Two companies will be picked for each mineral, four in all.

A Techno-Financial Committee, made up of specialists drawn from research organisations, technical institutes and public sector units, will evaluate the bids and recommend winners. The Governing Council, chaired by the Secretary of the Ministry of Mines, will make the final selection and sanction the support. A Project Management Agency will handle day-to-day administration. The Governing Council can also amend the scheme guidelines, subject to approval by the Union Minister of Mines.

When the money is released

The subsidy is paid in three tranches, each tied to how much the company has spent and how much equity it has put in:

Tranche

Milestone

Cumulative subsidy released (% of bid amount)

1

25% of committed capex spent; at least 15% of minimum required equity brought in

25%

2

50% of committed capex spent; at least 50% of minimum required equity brought in

50%

3

Plant commissioned; 100% of minimum required equity brought in

100%

Plants should start operating no later than three years after the Letter of Award, and must be commissioned within five years at the latest. If commissioning slips past the three-year mark, the support still unpaid is reduced under a tapering mechanism until the fifth year.

Why the government is doing this

Lithium, nickel and cobalt are key inputs for EV batteries and grid storage. The Cabinet note says global processing of critical minerals is concentrated in a few places. That leaves buyers exposed to geopolitical disruption, sudden price swings and export curbs. India relies largely on imported refined intermediate products and high-purity materials, partly because domestic processing is still at an early stage.

The PIB backgrounder says domestic processing is not viable under current market conditions. It points to high capital costs (advanced equipment, multi-stage conversion and strict environmental safeguards) and limited access to raw materials and suitable technology. Capex support is meant to offset these high upfront costs and make projects viable.

Expected impact

  • Investment: About ₹10,000 crore in processing projects

  • Capacity: Processing capacity of 60 kt for lithium and 100 kt for nickel, sized for projected demand by 2030

  • Imports: Domestic high-purity output should replace some imports, cutting the import bill and foreign exchange outgo

  • Downstream industry: Supply for battery material, battery cell and speciality steel makers, supporting existing manufacturing schemes

  • Jobs: Direct and indirect employment in processing and related manufacturing

How it fits India’s critical minerals plan

India’s list of 24 critical minerals includes lithium, nickel, cobalt, graphite and rare earths, and the country aims for net-zero emissions by 2070. The National Critical Mineral Mission (NCMM) was launched in January 2025. Under it, the Cabinet approved a ₹1,500 crore recycling scheme on 3 September 2025 to recover critical minerals from electronic waste, used lithium-ion batteries and other scrap. On the mining side, the Centre has so far auctioned 64 blocks of critical and strategic minerals, plus 11 exploration licence blocks. With this scheme, government support now covers exploration, mining, recycling and processing.

What to watch next

The official releases do not yet give application dates, the bidding timeline or detailed eligibility rules beyond the minimum plant sizes. Those should come with the scheme guidelines and bid documents from the Ministry of Mines. Companies in battery materials, mining and metals that are interested should watch the Ministry’s announcements.

Frequently asked questions

How much subsidy can one company get?

Up to ₹500 crore for a lithium plant and up to ₹900 crore for a nickel plant, within a 30% cap on eligible investment.

How many plants will be supported?

Four in total: two for lithium (minimum 30 kt each) and two for nickel (minimum 50 kt each).

How long do companies have to build the plants?

Commissioning is expected within three years of the Letter of Award, with an outer limit of five years. Support is tapered for delays beyond three years.

Sources

Press Information Bureau: “Cabinet Approves Capex Support Scheme to Promote Critical Mineral Processing with an Outlay of Rs.2,814 Crore for Lithium and Nickel processing”, 4 November 2026 (Release ID 2332476); PIB Research backgrounder “CAPEX Support Scheme to Promote Critical Mineral Processing”, 5 November 2026 (Release ID 2332964); Ministry of Mines.